Time and time again, Mechanical Dynamics & Analysis (MD&A) shows the global utility industry its strength, technical capability, and resource depth to serve as a premier alternative to the original ...
8 March 2004 � Alstom has set a benchmark by completing a generator rotor rewind in 22 days, against the industry standard of 42 days. This project was completed for the 660 MW Majuba power plant, ...
January 22 2004 – GE Energy received a contract of more than $540 000 from the Imperial Irrigation District (IID) for a hydro generator rewind project at an IID hydroelectric plant on the All American ...
EthosEnergy successfully completed the on-time delivery of two 223MVA, 200MW Generator rewinds worth $4m for two steam turbines owned by Indonesia Power. The Generators are located at Tanjung Priok ...